ABSTRACT In the Physical Work Project for the Development of the Qur’an Centre Phase 1 in th city of Pekanbaru, it is planned to be completed within 150 days. However, the implementation in the field was not in accordance with the time schedule at the start of the planning. This is due to the lack of workforce and material delays that affect the project completion time. The purpose of thie r…