ABSTRACT The construction project of BMW Showroom and Workshop in Pekanbaru city was planned to be completed within 240 days. However, the implementation in the field was not in accordance with the time schedule at the beginning of the planning. This is due to delays in several work items that affect the project completion time. The purpose of this research is to find out the optimization …