Optimalisasi Pelaksanaan Proyek Pembangunan Jalan Tol Menggunakan Metode Critical Path Method (Cpm) Pt. Hutama Karya (Studi Kasus Jalan Tol Pekanbaru-Padang Seksi 2 Sta 55+225 S.D 59+250)
ABSTRACT
Project development planning certainly requires proper analysis
and in accordance with the desired needs. This activity is very necessary
because it measures how much it will cost and how much it costs to build
the project. Road construction in Indonesia is currently growing rapidly,
especially in the current era. The success or failure of the implementation
of road construction projects is often due to the lack of planned project
activities and ineffective control so that project activities are not efficient.
Optimization of development time aims to prevent project delays and
minimize costs and accelerate development project activities. In the toll
road construction project the Pekanbaru Padang Toll road construction
work in section 2 STA 55+225 to 59+250 using the CPM method there is a
critical path where the work activities are land acquisition work,
construction work for kit and warehouse directors, foundation work,
column work
, Stressing girder work, slab work, asphalt coating work, other work and
finishing work. The scheduled duration of the project is 385 days, but after
being evaluated and analyzed by the CPM method, the project can be
completed within 374 days. This means that the project can be done 11
days earlier than the specified schedule.
Keywords: Project Management, Scheduling Optimization, CPM.