Evaluasi Dan Perencanaan Sistem Penyediaan Air Minum Di Kecamatan Bangkinang, Kabupaten Kampar
ABSTRACT
Drinking water needs in Bangkinang Subdistrict, Kampar Regency comes from wells,
river water and tap water where the quality and quantity have not been guaranteed.
Community water needs reach 191,61 L/sec in 2039, so it is necessary to plan a
drinking water supply system with raw water sources originating from the Kampar
River. Based on mass balance analysis, there are units that are able to process raw
water with quality according to the Minister of Health Regulation number 492 in 2010.
The planned treatment units are intake, pre-sedimentation, coagulation, flocculation,
sedimentation, filtration, disinfection and neutralization. This plan is also equipped
with supporting buildings, such as chemical plant buildings, water towers, and mud
processing units. Then the piped water distribution pipeline network planning is made
using EPANET 2.0 software. The simulation results show that the pipeline hydraulic
conditions for the planning area at peak hours have a speed of 0.30 m/s - 4.06 m/s, a
pressure of 8,57 m – 61,59 m, and the highest pressure loss of 4,35 m / km . Budget
costs incurred for the construction unit production and distribution piping system is
Rp. 108.405.000.000
Keywords: Bangkinang, EPANET 2.0, Kampar River, Piping, Simulation, Unit
Production, Water Treatment, Water requirement