ABSTRACT The Physical Development Work Project CWR-01 AKSI ADB UNRI Integrated Laboratory Building at the end of the project in October 2023 had a progress of 61.483%, it should have been planned to be 100% so that there was a deviation of 38.517%, so it is necessary to identify the risk of delay. The purpose of this study was to identify risk factors for delay based on literature studies, det…