Evaluasi Time Schedule Menggunakan Network Planning Pada Proyek Pembangunan Gedung Upip Rumah Sakit Jiwa Tampan Pekanbaru
Time schedule is a detailed timeline is provided for each piece of work, raging from parts beginning to end warker. Part research purproses evaluate work schedule and determine the trajectories that occur in network planning. Determine the work that has the possibility, to accelerate the evaluation of the time schedule by using network diagram obtained by the number of passes as much as 12 that consists of 5 critical path and 7 tracks noncritical. There are 19 items of work are included in the critical path and 26 work item noncritical. After the acceleration of some work item are incuded I the result obtained critical path project completion time is faster firstly a duration of 22 weeks to 21 weeks.
Keyword : Time Schedule, Network Planning, Critical Path.