Evaluasi Time Schedule Menggunakan Network Planning Pada Pekerjaan Pembangunan Gedung A Rumah Sakit Daerah Pekanbaru
Time Schedule (work plan) is a detailed timeline is provided for each piece of work, starting from the beginning until the end of the work piece. Objective studies evaluating the work schedule and specify the path that occurs in network planning. Determining the work included in the critical path. Determining jobs are likely to be accelerated. Conclusions based on the evaluation of the time schedule by using network diagram obtained by the number of passes as much as 432 that consists of 102 tracks critical and noncritical path 330. There are 38 items of work are included into the path of critical and noncritical 7 work items. After the acceleration of some of the work items are included in the results obtained critical path project completion time is faster, firstly a duration of 100 weeks to 97 weeks.
Key Words : Time Schdule, Network Planning, Critical Path