Tinjauan Penggunaan Alat Berat Pada Pekerjaan Lapis Pondasi Agregat Kelas B Jalan Swakarya Kecamatan Tampan Kota Pekanbaru
Heavy epuipment plays an important role because it can facilitate and assist employees in completing the project, especially for projects in a large scale. Heavy equipment which is used in a project must be considered because it affects the time and cost of the project. This research aims to Analysis of Equipment Usage in Base Layer Class B Aggregate Works at Swakarya Road Districts of Tampan Pekanbaru City. In this study, for the work of Aggregate Base Class B is calculated using the three alternatives, of the three alternatives, alternative A cheaper compared to alternative B and C. Conclusions obtained are: for alternative A is repuired to work for one days wheel loader 1 unit, 29 units of dump truck, 2 units of motor grader, 3 units of vibratory roller, 7 units of water tank truck. With the total overall cost of Rp. 108.395.940, 66.
Keywords : productivity, time and cost