Analisis Resiko Kinerja Waktu Pelaksanaan Proyek Konstruksi (Studi Kasus Proyek Pembangunan Terminal Multi Purpose Dan Fasilitas Pendukung Di Kuala Tanjung, Sumatera Utara)
Based on field observation which was conducted toward the Contractor during the implementation period, condition of the Multi Purpose Stationl Construction Project and Supporting Facilities in Kuala Tanjung, North Sumatera is likely to experience delay in completion schedule as well as an increase in expense. The application of risk management as a part of project management is expected to be able to reduce the negative risk and increase the positive aspects which later will be effected to time performance.
The objectives of this research are to identify risk factors, analyzing probability and risk impact to cost performance of work before and after risk mitigation. The result of the risk identification obtained 19 risk factors have an impact on the time performance. The highest risk impact on the time performance is: change design for engineering, often change design and change design for construction.
The time performance before a risk mitigation is categorized in the moderate-scale impact; 10,43%.. Risk impact to the time performance after risk mitigation is categorized in the low-scale impact; 6,40%.
Key words: time delay, probability, impact, risk analysis, risk mitigation