PERENCANAAN PEMBUATAN TIME SCHEDULE PADA PEMBANGUNAN RUMAH TINGGAL BERLANTAI DUA DI KECAMATAN SUKAJADI KOTA PEKANBARU
Before the erection of a building, Time Schedule is one of the main processes carried out
to determine how long the project can be completed by outlining each work item starting
with determining the number of workers, calculating the duration of the work, making a
time schedule, calculating the weight of the work and making curve s . In this Final
Project report, the author makes a time schedule with a total building area of 348.7 m2
and calculates the number of workers, the weight of the work and the duration of the day
on each work item. The total duration of work on the residential housing construction
project is for 18 weeks (126 days).