ABSTRACT The implementation process of the Pekanbaru-Dumai Toll Road Section 2B has been delayed significantly. The work process for the 3.85 km Toll Road project which should have been completed within 13 months starting from April 2018 has not been completed until the end of April 2019. The critical path method can find out critical paths, where a job from the project cannot be completed…