ABSTRACT Riau, there were cost shifts and schedule delays caused by slow decision making, funding constraints and design issues resulting in 4 Contract Change Orders (CCO). At week 52, which coincided with the end of the project implementation plan, the work realization only reached 45.54% with a deviation of -54.45%. In December 2022 the project entered into period I of the contract declare…