Evaluasi Time Schedule Menggunakan Network Planning Pada Proyek Pembangunan Gedung Rawat Inap Kelas Iii (Tahap Iii) Rsud Bangkinang
ABSTRACT
Time Schedule is a detailed division of work duration on each project
work. The problem in this study is the ineffectiveness of the duration of the work
and the amount of work done is not in accordance with the planned duration. The
purpose of the study was to evaluate the time schedule using the network planning
method to determine the critical trajectory by using Microsoft Project 2016
software and to accelerate the duration of work from its original duration by using
the acceleration method of adding labor, increasing working hours and
accelerating the work shift method. The conclusion of time schedule evaluation
using network planning is obtained as many as 50 work items which are included
in the critical path. After accelerating with three acceleration methods, it was
found that the results of accelerating the addition of manpower which cut the time
by 3 days from the original duration, acceleration by adding 2 hours of work cut 7
working days and acceleration with the work shift method which cut the duration
to 21 working days from the original duration. which is 206 working days.
Keywords: Time Schedule, Network Planning, Acceleration of Work Duration