ABSTRACT The Physical Development Work Project CWR-03 AKSI ADB UNRI Postgraduate building at the end of the project in September 2023 has progress amounting to 67.0759% should be planned at 95.5614% so that there is a deviation of 28.4855%, so it’s necessary to identify the risk of delay. The aim is to identify the risk of delays using the method Relative Importance Index, as well as det…